As part of ongoing upgrade work at Tuggerah Railway Station construction hours on Saturdays have been extended, starting in February until the project is complete in 2025.
Construction hours are now 7am to 6pm Monday to Friday and from 7am and 6pm on Saturdays.
Transport for NSW is planning to carry out electrical testing within the train station between 8pm and 2am on Wednesday, February 14, and Thursday, February 15.
Other work planned for February work includes: general construction works, including delivery and removal of plant and materials; surveying and site investigations; and adjustments to hoardings and fencing to facilitate construction works.
Also low-growing shrub vegetation will be removed to enable installation of temporary ramps and there will be: formwork, reinforcement and concrete pours; crane movements to assist with construction; earthworks including waste classification; and removal of waste materials.
Other work during February will include: relocation of lights, cameras and signs on both platforms; completion of new structural supports under Platform 1; and installation of pits for utility connections for the station.