Work is on schedule and progressing well on the major $178M upgrade of the Pacific Highway at Lisarow and providing an employment boost for hundreds of workers.
The work includes widening of the highway to provide two lanes in each direction between Ourimbah St and Parsons Rd.
A key feature of the 1.6km Lisarow upgrade is a new bridge across the rail line to replace the existing bridge at Railway Cres and 95 huge pilings and retaining walls have already been built to support the new bridge.
Transport for NSW Regional Director North, Anna Zycki, said the project was challenging and complex.
“When we’re working in a rail corridor, works that we would normally do in a number of weeks we have to completely re-think the planning, so we can get in and do that work in sometimes 72 hours or even 48 hours,” she said.
Zycki said the timetable for trains on the busy main northern rail line had to be taken into account so the line could be closed and the work done quickly.
Parliamentary Secretary for Central Coast, Adam Crouch, said during an on-site visit on August 28, much had been achieved in the 18 months since the project was started by contractor Daracon Group.
“It is powering along, with 50 percent of the above-ground engineering work such as foundations and the massive pilings now complete and more than 70 percent of the utility relocation work undertaken,” he said.
“Incredibly, more than six kilometres of trenching was required for water, sewer, gas, Telstra, NBN and electrical services.
“This project is a significant employment opportunity with about 1,000 workers from 156 companies employed on this site over the past 18 months and a very large proportion of those have been Central Coast locals.
“On any given day there are about 80 people on the construction site which just goes to show what a significant flow-on effect this $178M project is having for the Central Coast economy.”
The next steps include earthwork for the new road, installation of stormwater drainage and building retaining walls near Lisarow cemetery and The Ridgeway.
The Lisarow upgrade is a continuation of the $70M road upgrade of two lanes each way through Ourimbah, completed late 2018.
The roadworks also form part of other major upgrades through the Ourimbah to Lisarow rail corridor including improvements to accessibility and car parking set to start soon at Ourimbah, Lisarow and Narara railways stations.
Sue Murray