Changed traffic conditions will be in place as part of the Central Coast Hwy and Frederick St intersection upgrade at East Gosford.
Continuing storm water drainage and utility relocation work delayed due to wet weather in April has been rescheduled to start Sunday, May 17.
It is expected to take three weeks to complete, weather permitting. Work will be carried out between 8:00pm and 5:00am from Sunday, May 17 to Thursday, May 21, to minimise traffic disruptions.
The changed traffic conditions in place will include lane closures and a temporary reduced speed limit of 40km/h during work.
Traffic controllers will be in place to direct motorists.
The NSW Government allocated $6.5 million this year to upgrade the Central Coast Hwy to improve safety and traffic flow.
The upgrade will provide a dedicated right turn lane for motorists travelling eastbound on the highway into Frederick St.
Media release,
13 May 2015
NSW Roads and Maritime
Services media